Inspection OverviewCreated by HM
Total Scope
8
assigned items
Completed
0 / 8
0.0%
In Progress
0
items
Not Started
8
items
Weighted Progress
0.0%
0 / 15 pts
Status per Team
Team 1 (Ut grid)
Hikmat, Asyraf
0/3
- 2. Helideck Inspection w3Not Started
- 4. Boatlanding Inspection w3Not Started
- 5. Pad eye Inspection w2Not Started
Team progress: 0 of 3 done
Team 2 (Timber)
Hadri, Anggara
0/3
- 6. Cups Inspection w1Not Started
- 7. Boroscope w2Not Started
- 8. UT Grid w2Not Started
Team progress: 0 of 3 done
Team 3 (Ut grid)
Nabeel, Alagar
0/2
- 1. Ad hoc verification w1Not Started
- 3. Timber Inspection w1Not Started
Team progress: 0 of 2 done
Performance & Workload Analysis
| Team | Items Done | Points Done | Target Points | % Productivity | Performance |
|---|---|---|---|---|---|
| Team 1 | 0 | 0 | 8 | 0.0% | No Progress Yet |
| Team 2 | 0 | 0 | 5 | 0.0% | No Progress Yet |
| Team 3 | 0 | 0 | 2 | 0.0% | No Progress Yet |
% Productivity = (Points Done / Target Points) x 100% ยท Points = sum of weights of completed jobs
Analyst Conclusion
No team has completed any work yet; the entire workload (15 points) is still open. Team 1 carries the heaviest remaining workload at 8 points, including Helideck Inspection, Boatlanding Inspection (weight 3) which are high-risk and weather-dependent, so weather windows and safety support should be prioritised.